Client: Petrofac
Date: November 2012
Supplied stone to construction site and undertook the task of unsuitable materials disposal.
EMN Plant supplied and delivered structural fills, aggregates and recycled material to Petrofac for the construction of the Shetland Gas Plant. At our peak we supplied up to 1,800 ton in 1 day with 9 trucks.
Unsuitable material was also removed from the site to either be recycled or disposed of.
At the peak of construction, EMN Plant was moving 1800 tonnes of material per day, with 9 trucks running 10 loads per day, each.